Chief Calogero Courthouse Generator Replacement
![court.jpg](https://static.wixstatic.com/media/f64d84_4edc9ba6402641aba9eb8b550ed599e5~mv2.jpg/v1/fill/w_775,h_316,al_c,q_80,usm_0.66_1.00_0.01,enc_avif,quality_auto/court.jpg)
Client: LA Facility Planning & Control
Contact: MArk Bradley
Location: New Orleans, Louisiana
Project Cost: $650,000
Complete: In Progress
​
YKH Consulting undertook a project for LA Facility Planning and Control to replace their current 300 KW emergency generator and above-ground fuel tank. This involved removing the old generator, tank, electrical conductors, and conduit, and installing a new 350 KW natural gas generator on a raised platform.
YKH coordinated with the local natural gas provider to ensure a reliable supply and managed the project to minimize disruptions, allowing the building to remain occupied and operational throughout the upgrade.